The $3.5 billion SDSU Mission Valley project

How voters gave San Diego State the old stadium site in 2018, what the $3.5 billion, 15-year plan includes and what it has built so far in Mission Valley.

San Diego voters made their biggest land decision of the last decade over a parking lot with a football stadium in the middle of it. The city's stadium stood in Mission Valley for more than fifty years, on land the city owned. When the Chargers left for Los Angeles in 2017, the question became what to do with roughly 130 acres of flat, transit-served real estate in the middle of town. In November 2018 voters picked San Diego State University over a competing private plan. Eight years on, the first phase is built, and the larger plan, valued at $3.5 billion, is rolling out in stages over fifteen years. This is the decision, the project and the arguments that came with both.

What was on the site

San Diego Stadium opened in Mission Valley in 1967. The Chargers played there from that year, the Padres from their start in 1969 until they moved to Petco Park in 2004, and San Diego State football from 1967. Qualcomm held the naming rights from 1997 to 2017. The Chargers, in San Diego since 1961, left for Los Angeles in 2017. After that the Aztecs were the stadium's main tenant, and the question of the site's future could not wait.

The stadium sat on about 132 acres of city-owned land beside the San Diego River, with the trolley's Green Line running past and Interstates 8 and 15 close at hand. By the plain measure of a real estate analyst, it was one of the best undeveloped sites in the region.

Two ballot measures, one site

The November 2018 ballot put two competing measures on the site's future in front of city voters.

  • Measure G was a citizens' initiative, called SDSU West. It allowed the city to sell about 132 acres to San Diego State University at fair market value, as of October 2017, and it laid out a plan: a stadium for the university's football team and other uses, a university campus extension, housing, offices, hotels and a river park, with nearly 90 acres of parkland, habitat and open space.
  • Measure E was the SoccerCity proposal, from a private development group, for a Major League Soccer stadium with housing, offices, retail and a park, in hopes of landing a team for San Diego.

Measure G passed with roughly 54 percent of the vote, and Measure E failed. That gave the university the site, subject to the sale's terms and the approval of the California State University system and the city.

The arguments are worth remembering, because each held together on its own terms.

  • Supporters of SDSU West said the university needed room to grow, that a public university would look after the land better than a private developer would, and that the plan came with a large park along the river.
  • Supporters of SoccerCity said a privately built stadium and development would bring a Major League Soccer team to the city, privately financed, along with a large mixed-use district.

Both sides also made claims about traffic, cost and the future of professional soccer in town. The vote settled which plan went forward. What happened afterward, including an MLS team's arrival at the new stadium, comes below.

The $3.5 billion plan

The project that followed is big. As described in coverage of the university's plan, the Mission Valley development includes:

  • A stadium for football and other events, the first and most visible piece.
  • Housing on the valley floor. Campaign materials in 2018 described roughly 4,500 homes, though the final number depends on the phases the university builds.
  • Offices and hotels, which make it a mixed-use district and not just a campus.
  • A river park along the San Diego River, restoring habitat and creating open space for the public.
  • A timeline of about 15 years, with the work done in phases rather than all at once.

The $3.5 billion total is a projection across all phases. Spread over fifteen years it averages about $233 million a year ($3,500 million divided by 15). That is a number for scale, not a budget. Real spending follows the phase schedule, the financing and the market.

The first phase: Snapdragon Stadium

The stadium opened August 19, 2022, with 35,000 seats that can expand to 55,000, at a cost of about $310 million. It stands on the old San Diego Stadium site. The older stadium, up from 1967 until its demolition in 2020 and 2021, is gone. Qualcomm bought the naming rights in December 2021, putting the company's name back on the site as Snapdragon Stadium. For the naming history, see qualcomm, a city headquarters and a stadium name and Snapdragon Stadium: from Qualcomm Stadium to Snapdragon.

The tenants show how the place gets used:

  • San Diego State football, the original reason for the plan.
  • San Diego FC, the Major League Soccer club awarded to the city on May 18, 2023, which began play in 2025 as the league's thirtieth club. In its first season it finished first in the Western Conference with 63 points, an expansion record. See San Diego FC's record first season.
  • The San Diego Wave, the National Women's Soccer League team, which moved to Snapdragon from Torero Stadium in 2022. See San Diego Wave FC at Snapdragon.
  • The Holiday Bowl, since 2024.
  • The 2028 Olympics. The stadium will host 11 Olympic soccer matches in July 2028 under the name San Diego Stadium. See The 2028 Olympic matches at Snapdragon.

There is a twist on the 2018 argument in all this. The measure that won was the one that did not promise a professional team, and the stadium built under it hosts one anyway. That does not settle the old debate. It does show that a public university's stadium and a pro club can share a building.

The decision in dates

Date Event
1967 San Diego Stadium opens in Mission Valley
1997 to 2017 Qualcomm holds the stadium's naming rights
2017 The Chargers leave for Los Angeles
November 2018 Voters approve Measure G for SDSU West and reject Measure E
2020 to 2021 The old stadium is demolished
December 2021 Qualcomm buys the Snapdragon Stadium naming rights
August 19, 2022 Snapdragon Stadium opens
May 18, 2023 San Diego is awarded an MLS team
2025 San Diego FC plays its first season
July 2028 Eleven Olympic soccer matches are scheduled for the stadium

Snapdragon Stadium in numbers

Measure Figure
Opened August 19, 2022
Seats 35,000, expandable to 55,000
Cost About $310 million
Soccer attendance record 34,506 (March 2025)
Planned Olympic matches 11, in July 2028
Overall project value $3.5 billion over about 15 years

The stadium's own cost, about $310 million, is under a tenth of the overall $3.5 billion. Call it 8.9 percent: $310 million divided by $3,500 million. That shows how much is still ahead. Nine-tenths of the planned investment is housing, offices, hotels, the river park and the infrastructure tying them together.

After the stadium

The remaining pieces, the housing, offices, hotels, river park and other university facilities, come in later phases. That is the point of a 15-year plan. A stadium goes up in a few years. A neighborhood takes longer, because housing and offices follow demand, financing and the pace of the university's own needs.

What a visitor sees now is the stadium bowl and the construction around it. The district ties into the rest of the region by trolley and by freeway. The Green Line stops at the Stadium station, and a rider on the same line reaches the SDSU Transit Center and the campus on Montezuma Mesa. For the transit geography, see Mission Valley by trolley, stop by stop and Mission Valley.

Questions a big project raises

A project this size throws off questions with no final answers, and the useful ones are the ones to watch:

  1. Does the housing get built on schedule? The phasing depends on markets and financing.
  2. How does the river park take shape? Restoring a river corridor, with trails and habitat, is a long job with its own permits.
  3. How do event days work? A stadium holding 35,000 to 55,000 people on a valley site needs a transit and parking plan that works on game days, concert nights and soccer matches alike. The trolley is central to it.
  4. What does it do to the neighborhood? Mission Valley has long been a district of freeways, hotels and shopping centers. Adding housing and open space turns it toward a place where people live, which is the goal.

The land was city property before the sale, so the council and the mayor were part of the story from the start, and the Independent Budget Analyst, an office that works for the council, writes analyses of ballot measures and development deals. See San Diego City Council and San Diego Independent Budget Analyst.

Why it matters beyond the valley

For San Diego State, the project is a chance to grow where the mesa has no room for a bigger campus. For the city, it swapped a stadium with an uncertain future for a mixed-use district, without the city running the project. For the region, it put a major soccer stadium on a transit line and made the valley a likelier site for the dense housing the city needs.

The history behind it is the university's long relationship with the valley; see San Diego State, 1897 to Mission Valley and The Chargers in San Diego, 1961 to 2017. Anyone who wants to follow the project from here can do it without special access: the university and the city publish their documents, the council and the Independent Budget Analyst discuss them in public, and the stadium is open on game days for anyone who wants to see the first phase for themselves. A fifteen-year plan will not be finished until the late 2030s, so the final verdict is some years off. The stadium, the soccer, the football and the Olympic matches to come are already part of the city, and the rest is still going up.