Getting a building permit in San Diego

How the Development Services Department handles permits, online accounts, the intake, review and issuance stages, Simple Permits, counter hours and inspections.

Building a deck, replacing a water heater, adding a unit over the garage and opening a restaurant all start at the same place in the City of San Diego: the Development Services Department, known as DSD. The department takes in applications, reviews plans, issues permits and schedules inspections. Most of that work now happens online, which changes what a first-time applicant has to do.

Start with an account

DSD says user accounts are required to submit all online permit applications. The department's home page has an Apply Now section, a tutorial, and a short questionnaire that asks which permit you want. A list of permits available online is posted there; if the permit you need is not available online, the page says to contact the department to apply. Some permits have their own pathways:

  • a no-fee street tree permit
  • a news rack permit
  • a residential rooftop-mounted solar photovoltaic permit
  • a transportation permit, which is not the same as a traffic control permit
  • Simple Permits, described below

The department's phone number for appointments is 619-446-5000.

Simple Permits: when no plans are needed

Homeowners, property owners and licensed contractors can get a no-plan mechanical, electrical and plumbing permit, called a Simple Permit, for minor installations in single-dwelling units, duplexes or townhouses. The property must be outside a historic district or not individually designated as historic. Eligible work includes:

  • Mechanical: installing a forced air unit or air conditioner, installing exhaust fans, replacing furnaces.
  • Electrical: meter resets, adding circuits, relocating outlets or rewiring, temporary power poles for construction sites and electric vehicle charging stations for private garages.
  • Plumbing: replacing a water heater (tankless types excepted), repairing water or sewer piping or gas lines, repairing or replacing drains, installing a water softener and pressure reducing valves.

The city points applicants to Information Bulletin 103 for details. Plans and calculations are required for multi-family, commercial and other non-residential buildings and for all properties designated as historic or in historic districts, with Information Bulletin 581 explaining designated historical resources. Owner-builders must also upload the Owner-Builder Verification Form DS-3042. A licensed contractor receives the permit as soon as the application is completed and submitted.

Three stages and the timeline page

For permits that require plan review, DSD publishes a Permit Processing Timeline, updated weekly, showing approximate days for three stages:

  1. Intake. The queue time from first upload to pre-screen, including initial screens and resubmitted screens.
  2. Review. The time from the start to the finish of project review, including first reviews and rechecks. A project is considered complete once the set-up fees are paid, and first reviews begin then.
  3. Permit issuance. The queue time after review and the time staff take to confirm all requirements are met.

DSD says these are weekly estimates and that actual times vary with the number of applications and the completeness of documents. As of November 13, 2026, the issuance stage was listed at about one business day for a building permit, with four projects in the queue; for a building permit under rapid review, one business day with seven in the queue; for a construction change, one day with three; for demolition and stand-alone mechanical, plumbing and electrical permits, four days with eight in the queue; for grading, public improvement and mapping, five days with twelve; and for a sign permit, one day with four. Those are issuance numbers only, after review, and they change weekly. how long a building permit takes looks at the whole timeline.

What happens after you submit

When you submit a new application, DSD checks that everything is complete and determines the fees. After plan-check and other fees are paid, the project enters the review queue for each discipline and is assigned to a reviewer. Each discipline issues its comments in a cycle report. You cannot upload corrected plans until every discipline has finished its cycle, and when several disciplines ask for corrections, the responses must be consolidated into a single file and uploaded together, with answers to every discipline's comments at once.

The department's tips: provide an accurate inspection contact, review the requirements to avoid delays, use the virtual appointment options for faster intake and issuance, and check its Fast Track Your Permit page for programs that can speed up a project.

Counters and appointments

Public counters are open 7 a.m. to 4 p.m. Monday through Thursday and 10 a.m. to 4 p.m. on Friday. All counters close from 11:30 a.m. to 12:30 p.m. Walk-in services are not available after 3 p.m., and walk-in customers who arrive after 1 p.m. may not be seen. Appointments are made by phone or online, and virtual appointments are an option.

After the permit: invoices, status and inspections

The home page has separate tools to pay or find an invoice, schedule an inspection, search for project status by permit type, and use an interactive map to find permit information. A Permitting Center Dashboard summarizes permit data, inspections and Building and Land Use Enforcement cases. Construction changes after a permit is issued have their own pathway under the same permit.

When there is no permit

Work done without a permit can lead to an enforcement case. DSD's Building and Land Use Enforcement team, BLUE, takes reports at 619-236-5500, and a record of cases can be searched online. For zoning, the Zoning and Parcel Information Portal (ZAPP) shows what a site is zoned.

An accessory dwelling unit needs a building permit with no exceptions; see Adding an accessory or junior unit in San Diego. A new business may need separate approvals in addition to the Business Tax Certificate; see Starting a business and the Business Tax Certificate. For larger projects, the Planning Department's community plans set the context. The department's pages are the authority for fees and forms.