How long a building permit takes
How San Diego's Development Services Department measures permit time in three stages, what its weekly estimates say, and what slows a project in review.
Ask three San Diego homeowners how long their permit took and you will hear a week, four months and a year. All three can be telling the truth. "The permit" is not one wait. It is a chain of queues, and the city's Development Services Department, DSD to everyone who has dealt with it, publishes a page that breaks the chain into links and refreshes the numbers every week. Reading that page is the quickest way to set expectations, and knowing what sits behind it is the quickest way to shorten your own wait.
This one is for the person about to apply for a building permit, whether for a kitchen remodel, a deck, a garage conversion or a backyard unit. It covers the three stages DSD measures, what the November 2026 figures show, how a review cycle works and which habits turn a short wait into a long one. It is general information, not advice on a particular project; the department's staff and published manuals are the authority on any application.
Three stages, three clocks
DSD splits a permit's time into three parts:
- Intake. The queue time from the moment you first upload your documents until staff finish a pre-screen to check that the submittal is complete.
- Review. The time from the start to the finish of the project review, when the different disciplines (for example building, structural, mechanical, plumbing, electrical, fire and others, depending on the project) check the plans against the codes.
- Permit issuance. The queue time after review ends, plus the staff work of verifying that every requirement is met and every fee is in place before the permit goes out.
The page reports intake and review as averages in calendar days, and issuance as approximate business days along with the number of projects waiting in each queue. The difference matters. Intake and review depend heavily on the quality of what you submit. Issuance is mostly a matter of how long the line is, which is why the page can show it as a small number per permit type.
What the weekly estimates showed in November 2026
As of November 13, 2026, DSD's estimates for permit issuance, the last of the three stages, were:
| Permit type | Approximate business days | Projects in queue |
|---|---|---|
| Building permit | 1 | 4 |
| Building permit, rapid review | 1 | 7 |
| Building construction change | 1 | 3 |
| Demolition, stand-alone mechanical, plumbing, electrical | 4 | 8 |
| Grading, public improvement, mapping | 5 | 12 |
| Sign permit | 1 | 4 |
The numbers run small because issuance is the last step. A building permit that has been fully reviewed and approved waits roughly one business day for verification and release. Grading, public improvement and mapping permits take closer to a week because they involve more verification and usually bigger projects.
Do not mistake those for the total time to get a permit. They measure only the final queue. A project that sails through issuance in a day may have spent weeks in review, since the corrections traded between you and the plan reviewers happen in review, not issuance. DSD also notes that the figures are weekly estimates and that actual times shift with the volume of applications and how complete each submittal is.
How a review cycle works
Most of the elapsed time lives in review, and the department's description of it holds a few rules that catch first-timers off guard.
- A review begins only when the project is complete. The first review starts once the project is deemed complete, which happens after the setup fees are paid. A submittal missing a document or carrying an unpaid fee never enters the queue.
- Each discipline reviews separately and issues its own report. When a discipline finishes its cycle, it issues a cycle issues report listing what needs correcting. Your plans may come back with comments from several at once.
- You cannot answer one discipline at a time. Responses cannot be uploaded until every discipline has finished its cycle, and the resubmittal must answer all the comments together. A partial correction restarts nothing.
- Rechecks begin when all documents are uploaded. A recheck starts after you have uploaded every requested document, and then each discipline looks again.
The practical result is that the slowest discipline sets the pace for everyone. If four reviewers finish in a week and one takes three, you wait three weeks before you can answer any of them. Then the next cycle begins the same way. Two cycles mean two such waits. Four cycles mean four.
What drags a project out
The department's own advice for faster processing is short: submit complete and current documents, read the Project Submittal Manual and book a virtual appointment for help with setup or issuance. Those three tips point at the main causes of delay.
Incomplete submittals. A missing sheet, an unreadable scan or a blank form can send a project back to the start of intake. The Submittal Manual lists what each project type must contain, and checking your package against it before you upload takes less time than waiting for a rejection.
Slow responses. A cycle ends only when you send back all the corrections. Take two weeks to answer a comment letter and part of the clock on your project is your own.
Piecemeal corrections. Because every discipline's comments must be answered together, sending back an answer to the plumbing comment alone changes nothing. Gather them and resubmit once.
Changes after approval. A project that changes after plans are approved needs a construction change, which has its own estimate in the table above and its own review.
Unclear scope. A project described one way in the application and drawn another on the plans invites questions from reviewers. A short narrative that matches the drawings cuts down the number of cycles.
The tools around the process
DSD has put together a set of public tools that sit beside the application itself:
- The portal and Accela. Applications and documents go in online through the department's portal and the Accela system at aca.accela.com/SANDIEGO, and a tool called OpenDSD lets anyone look up the history of a project or address.
- The Permitting Center Dashboard. It shows overall permit data, inspections and enforcement information for the department.
- Workflow status definitions. A mapping document explains what each status in the system means, so "in review" and "awaiting resubmittal" are not guesses.
- Virtual appointments. Staff are available for help with setup or issuance.
- Counters. The department's counters are open 7 a.m. to 4 p.m. Monday through Thursday and 10 a.m. to 4 p.m. on Friday, closed from 11:30 a.m. to 12:30 p.m. every day, with no walk-ins after 3 p.m. The main number is 619-446-5000. Check the department's page before you go, because hours and procedures change.
For the department's role in the city, see Development Services Department. The step-by-step version of the application is in Getting a building permit in San Diego, and backyard units have their own program, described in Adding an accessory or junior unit in San Diego and adding a companion unit: the permit path.
A walk through the clocks
Say a homeowner in a mid-city neighborhood wants to remodel a kitchen and move a wall. What follows is hypothetical, a trip through the three clocks and not a forecast.
On a Monday she uploads plans and forms and pays the setup fees. Intake staff run a pre-screen. If something is missing, the project goes back and the clock restarts, so she has already checked the manual and uploaded everything. The project is deemed complete.
It enters review. The structural reviewer has comments on the wall. The plumbing reviewer approves. The building reviewer wants a note changed on the plans. Each issues a cycle issues report when its review is done. She cannot upload anything until the last discipline has finished, so her wait for the first cycle is as long as the slowest review. She gathers every comment, has her designer revise the drawings and uploads them in one package. A recheck begins when every requested document is in. This time every discipline signs off.
The project moves to issuance. In November 2026 a building permit was waiting about one business day with four projects ahead of it. The permit goes out. Work can start, and inspections follow as it proceeds.
At each stage a different habit saved or cost time: a complete first submittal, a single complete response, a quick one. None of it required knowing anyone at the department.
When the work starts first
Some projects start without a permit and get found out later. The department's Building and Land Use Enforcement unit, at 619-236-5500, handles complaints about construction without permits. Anyone who has done work without a permit, or who is unsure whether a project needs one, should ask DSD before going further, because what requires a permit is set by the city's code and the department.
Beyond the building permit
Not every project is only a building permit. Larger ones may bring in land-use review and the city's Planning Department, which coordinates 52 community planning areas covered by 49 community plans. See Planning Department for how planning differs from permit review. The big projects that reshape neighborhoods, such as the redevelopment around Mission Valley, take a much longer road than a kitchen. DSD's weekly page makes the ordinary stretch of that road visible, and for most homeowners that is the stretch that counts.